Voyage details and related metadata, reports, events and data.
IN2021_E03 - is a Marine National Facility voyage
Title: Equipment Trials and Calibrations 2021
Voyage details on MNF site: https://mnf.csiro.au/en/Voyages/IN2021_E03
Period: 2021-11-30 22:30 to 2021-12-07 22:10 UTC
Duration: 6.99 days
From: Hobart To: Hobart
Ship: Investigator (RV) [details]
Description:
The primary voyage objective for these voyages, are for the Marine National Facility (MNF) to calibrate and commission new, upgraded and existing critical equipment (with sea trials and personnel training) onboard RV Investigator for upcoming voyages in the 2021 schedule and beyond.
Specifically, work will focus on the seagoing testing and trials of MNF’s new Giant Piston Corer with 24m maximum barrel length capability, principally supported by the Geophysical Survey and Mapping team and marine geoscientists from UTAS.
Additionally the voyage will finalise the calibration of the CTD#2 winch with Rapp Macgregor personnel, crew and support staff.
Ancilliary Objectives (Piggybacks)
The following anciliary voyage objectives are targeted where they don’t limit or impact above priorities.
- A small contingent of scientists will advise on QAQC for collection of piston coring samples. The scientific advisors have supported voyage planning by advising appropriate sites of interest that target reduced risks to equipment and personnel, aid commissioning and gain scientific insight, notable thanks to Alix Post and Scott Nichol from Geoscience Australia. Due to traveling restrictions, Martin Jutzeler and Acacia Clark have agreed to fill in this QAQC role onboard the voyage. If cores are successful and of scientific value, they will be provided to the scientific advisors for analysis post voyage in accordance with CSIRO’s Data and Sample Management Policy.
- Underway aerosol particulate CO2 sensor upgrade & replacement, testing & monitoring underway by Craig Neill from O&A.
Project: Investigator - general vessel operations, gear trials, etc. [details] Primary
Underway data from NRUD - see this voyage
Voyage extents: 44° 37.0' S to 42° 53.2' S 146° 49.5' E to 148° 47.7' E Get voyage track shapefile Get CSV
Marlin Metadata:-
Cruise Summary Report at SeaDataNet:-
Participants - on ship:-
Name | Role | Organisation | Project |
---|---|---|---|
Jason Fazey | Chief Scientist | CSIRO National Collections and Marine Infrastructure | Investigator - general vessel operations, gear trials, etc. |
This list includes those that may have only been on part of the voyage. See voyage reports on 'Reports and Maps' tab for details.
Marine National Facility Reports - plans, summaries and data processing
-
IN2021_E03 Voyage Plan
- includes objectives, investigator details, proposed data collection, voyage track and equipment to be used.
-
IN2021_E03 Voyage Summary
- includes preliminary results, voyage narrative, types of data collected with C77/ROSCOP codes.
-
IN2021_E03 ADCP Data Processing Report
- details of data processing steps, calibration information, instruments used and any issues with the data.
-
IN2021_E03 Underway Data Processing Report
- details of data processing steps, calibration information, instruments used and any issues with the data.
- View Survey map
Publications, reports and datasets from this voyage.
Dataset
- Fazey, Jason; Boyd, Matt; Berry, Chris; Kuna, Nelson; Navidad, Cisco; Taylor, Charlie; Plunkett, Tom (2022): IN2021_E03 South-East Tasmania Bathymetry 5m - 210m Multi-resolution AusSeabed products. v1. CSIRO. Data Collection. 10.25919/fzt3-a364
- Tilbrook, Bronte; Neill, Craig; Akl, John (2022). Integrated Marine Observing System (IMOS) sea surface and atmospheric fCO2 measurements in the Southern Ocean, South Pacific, Indian Ocean onboard R/V Investigator in 2021 (NCEI Accession 0253535). [indicate subset used]. NOAA National Centers for Environmental Information. Dataset. 10.25921/thsr-dd03
Journal Article
- Lucieer, Vanessa,Flukes, Emma,Monk, Jacquomo,Walsh, Peter (2024) Geomorphometric maps of Australia’s Marine Park estate and their role in improving the integrated monitoring and management of marine ecosystems. Frontiers in Marine Science 10 pp-. 10.3389/fmars.2023.1302108
Search for publications, reports and datasets from this and other voyages
Data publishing
This is a list of online datasets hosted by CSIRO. Other processed datasets hosted by collaborating organisations may be found on the 'Metadata' or "Reports, Publications and Maps' tab.
Use the Get data link on the right to extract data using the NCMI Data Trawler.
Data Stream | Data Summary | Get data | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
ADCP Data |
|
Get Data from Trawler Download the 5 minute ADCP OS75nb Data (NetCDF format) Download overview plots of collected OS75nb ADCP data Download overview plots of collected OS150nb ADCP data Download the 5 minute ADCP OS150nb Data (NetCDF format) |
||||||||||||||
Gravity Measurements | No data | |||||||||||||||
Multibeam echosounder |
|
Get Data from Trawler |
||||||||||||||
pCO2 |
|
External link - download datafile at IMOS Data fields and units document (.pdf) |
||||||||||||||
Sub-bottom profiler |
|
Get Data from Trawler |
||||||||||||||
Singlebeam echosounder |
|
Get Data from Trawler |
||||||||||||||
Underway |
|
Get Data from Trawler Download the 10-second Underway data (CSV format) Download the 5 minute Underway data (CSV format) Download the 5 second Underway data (netCDF format) Download the 1 minute Underway data (CSV format) Download the 5 second Underway data (CSV format) |
Caveat: this event log was authored on the voyage using either a standalone logging system called ELOG or more recently an inhouse event logging tool called Everlog. For this reason, some positions are unknown and may be resolved using the logged time and the underway dataset for the voyage.
Search for events from this voyage and others
Events ordered by start time:- Click on column header to sort. Use link on 'When' to see full details. Use the CSV button at the bottom to export data.
When (UTC) | Latitude | Longitude | Instrument | Identifier | Action | Log | Subject / Comments |
---|---|---|---|---|---|---|---|
2021-11-26 19:12 [view ] | SVP [view] | SVP | Sound velocity probe event SVP Applied | ||||
2021-11-27 15:28 [view ] | SVP [view] | SVP | Sound velocity probe event SVP Applied | ||||
2021-11-27 21:44 [view ] | SVP [view] | GSM | Sound velocity probe event SVP applied | ||||
2021-11-30 22:10 [view ] | -42.8864 | 147.3388 | Techsas 1 [view] | Start | Techsas 1 event start techsas with new mission | ||
2021-11-30 22:10 [view ] | -42.8864 | 147.3388 | Techsas 2 [view] | Start | Techsas 2 event start techsas with new mission | ||
2021-11-30 22:36 [view ] | -42.8864 | 147.3388 | Underway Merger | Start | Underway merger event | ||
2021-11-30 23:34 [view ] | -42.9358 | 147.3794 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start Logging EM710 | ||
2021-11-30 23:57 [view ] | -42.9754 | 147.3743 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Stop logging vessel stopped | ||
2021-12-01 00:01 [view ] | -42.9760 | 147.3752 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event | ||
2021-12-01 00:04 [view ] | -42.9760 | 147.3752 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event | ||
2021-12-01 00:05 [view ] | -42.9756 | 147.3753 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event | ||
2021-12-01 00:15 [view ] | -42.9757 | 147.3753 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging SBP stationary on site | ||
2021-12-01 00:15 [view ] | -42.9757 | 147.3753 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging stationary on site | ||
2021-12-01 00:18 [view ] | -42.9757 | 147.3752 | Ozone Monitor [view] | Start | Atmospherics | RVT1 - restart | |
2021-12-01 01:10 [view ] | -42.9757 | 147.3753 | TSG [view] | UWY Seawater | Thermosalinograph events | ||
2021-12-01 01:11 [view ] | -42.9757 | 147.3753 | pCO2 [view] | UWY Seawater | pCO2 event | ||
2021-12-01 01:22 [view ] | -42.9757 | 147.3753 | GPC [view] | Field Ops | Giant Piston Corer VOYAGE TOOL BOX TALK ON gpc hAZARDS AND OPERATIONAL PREPARNESS. | ||
2021-12-01 01:22 [view ] | -42.9757 | 147.3753 | GPC [view] | Giant Piston Corer VOYAGE TOOL BOX TALK ON gpc hAZARDS AND OPERATIONAL PREPARNESS. | |||
2021-12-01 01:48 [view ] | -42.9757 | 147.3753 | SVP [view] | SVP | Sound velocity probe event SVP Applied | ||
2021-12-01 01:48 [view ] | -42.9757 | 147.3753 | SVP [view] | SVP | Sound velocity probe event SVP Applied | ||
2021-12-01 01:48 [view ] | -42.9757 | 147.3753 | SVP [view] | GSM | Sound velocity probe event SVP Applied | ||
2021-12-01 01:48 [view ] | -42.9757 | 147.3753 | SVP [view] | SVP | Sound velocity probe event SVP Applied | ||
2021-12-01 04:49 [view ] | -42.9759 | 147.3753 | GPC [view] | Giant Piston Corer cph vertical and gpc at working height | |||
2021-12-01 05:28 [view ] | -42.9759 | 147.3752 | GPC [view] | Giant Piston Corer pipe barrels install start | |||
2021-12-01 06:28 [view ] | -42.9759 | 147.3752 | ADCP [view] | Start | ADCP Event both started | ||
2021-12-01 06:29 [view ] | -42.9759 | 147.3752 | Drop Keel [view] | Drop Keels event Both lowered to flush with Gondola. | |||
2021-12-01 06:47 [view ] | -42.9759 | 147.3752 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event | ||
2021-12-01 06:48 [view ] | -42.9759 | 147.3752 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event | ||
2021-12-01 06:48 [view ] | -42.9759 | 147.3752 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event | ||
2021-12-01 06:54 [view ] | -42.9759 | 147.3752 | GPC [view] | Giant Piston Corer 2nd core barrel fitup | |||
2021-12-01 06:54 [view ] | -42.9759 | 147.3752 | GPC [view] | Field Ops | Giant Piston Corer 2nd core barrel fitup | ||
2021-12-01 07:32 [view ] | -42.9759 | 147.3752 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event | ||
2021-12-01 07:32 [view ] | -42.9759 | 147.3752 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event | ||
2021-12-01 07:32 [view ] | -42.9759 | 147.3752 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event | ||
2021-12-01 07:43 [view ] | -42.9775 | 147.3744 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event | ||
2021-12-01 07:43 [view ] | -42.9775 | 147.3744 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event | ||
2021-12-01 07:43 [view ] | -42.9791 | 147.3746 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | GSM | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | SVP | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | Field Ops | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | GSM | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | GSM | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:26 [view ] | -43.0823 | 147.4261 | SVP [view] | GSM | Sound velocity probe event SST = 15.70 SAL = 32.22 | ||
2021-12-01 08:30 [view ] | -43.0913 | 147.4415 | EM122 [view] | SVP | GSM_in2021_e03 | ||
2021-12-01 09:01 [view ] | -43.1464 | 147.5355 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-01 09:01 [view ] | -43.1464 | 147.5355 | SVP [view] | SVP | Sound velocity probe event | ||
2021-12-01 09:32 [view ] | -43.1997 | 147.6265 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start backscatter line 0022 | ||
2021-12-01 09:32 [view ] | -43.1997 | 147.6265 | EM710 [view] | SVP | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start backscatter line 0022 | ||
2021-12-01 09:32 [view ] | -43.1997 | 147.6265 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start backscatter line 0022 | ||
2021-12-01 10:07 [view ] | -43.2493 | 147.7141 | SVP [view] | SVP | Sound velocity probe event | ||
2021-12-01 10:07 [view ] | -43.2493 | 147.7141 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-01 10:08 [view ] | -43.2507 | 147.7204 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event End backscatter line 1 | ||
2021-12-01 10:43 [view ] | -43.2741 | 147.8278 | SVP [view] | SVP | Sound velocity probe event RapidCTD prior to backscatter Line 4 | ||
2021-12-01 10:43 [view ] | -43.2741 | 147.8278 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-01 10:52 [view ] | -43.2759 | 147.8458 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-01 11:01 [view ] | -43.2760 | 147.8615 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Line number 0025 also has part of line. Missed change as was helping deploy camera | ||
2021-12-01 11:38 [view ] | -43.2762 | 147.9008 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-01 11:38 [view ] | -43.2762 | 147.9008 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-01 12:20 [view ] | -43.2706 | 148.0365 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-01 12:39 [view ] | -43.2658 | 148.1138 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-01 13:11 [view ] | -43.2584 | 148.2326 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Offshelf | ||
2021-12-01 13:11 [view ] | -43.2582 | 148.2355 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Start for off shelf operations | ||
2021-12-01 13:12 [view ] | -43.2582 | 148.2355 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Change pulse settings and window size for slope mapping | ||
2021-12-01 13:14 [view ] | -43.2577 | 148.2441 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Change logging range as vessel goes over shelf | ||
2021-12-01 13:22 [view ] | -43.2559 | 148.2729 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Change reader to em122 | ||
2021-12-01 13:32 [view ] | -43.2546 | 148.2954 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-01 13:48 [view ] | -43.2547 | 148.3080 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Further adjust settings for deeper water | ||
2021-12-01 16:01 [view ] | -43.2453 | 148.4533 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-01 16:40 [view ] | -43.2391 | 148.5418 | ME70 [view] | GSM | Kongsberg/Simrad ME70 shallow water multibeam scientific and fisheries echo sounder system event | ||
2021-12-01 17:35 [view ] | -43.2340 | 148.6449 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop logging stationary | ||
2021-12-01 17:39 [view ] | -43.2341 | 148.6450 | SVP [view] | SVP | Sound velocity probe event SVP applied while not logging | ||
2021-12-01 19:20 [view ] | -43.2322 | 148.6428 | GPC [view] | Field Ops | Giant Piston Corer deck t5 and start of CPH testing with am IR's | ||
2021-12-01 19:34 [view ] | -43.2324 | 148.6432 | ADCP [view] | Stop | ADCP Event | ||
2021-12-01 19:34 [view ] | -43.2324 | 148.6432 | ADCP [view] | Start | ADCP Event restarted without bottom tracking | ||
2021-12-01 21:41 [view ] | -43.2324 | 148.6424 | ME70 [view] | GSM | Kongsberg/Simrad ME70 shallow water multibeam scientific and fisheries echo sounder system event | ||
2021-12-01 21:46 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer CPH back on deck - Take 5 on assembly of components. Begin assembly of piston and warps. | ||
2021-12-01 23:57 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer Prestart complete_set up gpc start | ||
2021-12-02 00:22 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer stand down due to timings of activities and lunch and crew swap out to reduce risks of in water inattention | ||
2021-12-02 00:44 [view ] | -43.2327 | 148.6429 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-02 01:08 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer deck toolbox complete - CPH deploy started | ||
2021-12-02 01:10 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer filling barrels with sea water | ||
2021-12-02 01:13 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer CPH vertical. hose stopped. | ||
2021-12-02 01:16 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer take 5 complete - trigger. | ||
2021-12-02 01:24 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer trigger situated over head weight; begin lever arm install | ||
2021-12-02 01:28 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer hydrostatic charged to 50psi | ||
2021-12-02 01:33 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer level are, 35t shackle & rope bag fitted | ||
2021-12-02 01:37 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer pilot take5 complete; assembling pilot to pilot warp | ||
2021-12-02 01:42 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer Pilot warp secured to lever arm | ||
2021-12-02 01:44 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer take 5 - remove GPC for CPH compete | ||
2021-12-02 01:49 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer GPC deployed 50mtr. stop depth. recover CPH system. | ||
2021-12-02 01:58 [view ] | -43.2327 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer CPH secured to deck and inhibited | ||
2021-12-02 03:02 [view ] | -43.2339 | 148.6421 | ADCP [view] | Stop | ADCP Event stop to reduce interfence during corer testing | ||
2021-12-02 03:07 [view ] | -43.2345 | 148.6417 | GPC [view] | Field Ops | Giant Piston Corer 3138 stop depth - 3 min wait | ||
2021-12-02 03:12 [view ] | -43.2354 | 148.6412 | GPC [view] | Field Ops | Giant Piston Corer 3200 | ||
2021-12-02 03:24 [view ] | -43.2362 | 148.6406 | GPC [view] | Field Ops | Giant Piston Corer Unload trigger event | ||
2021-12-02 03:32 [view ] | -43.2367 | 148.6403 | GPC [view] | Field Ops | Giant Piston Corer Free of sea floor @4.4t max load,5m/m winch. | ||
2021-12-02 03:39 [view ] | -43.2372 | 148.6399 | ADCP [view] | Start | ADCP Event | ||
2021-12-02 04:37 [view ] | -43.2446 | 148.6364 | GPC [view] | Field Ops | Giant Piston Corer 250 mtr safety stop | ||
2021-12-02 04:42 [view ] | -43.2452 | 148.6361 | GPC [view] | Field Ops | Giant Piston Corer 100 mtr stop - CPH take 5 | ||
2021-12-02 05:03 [view ] | -43.2449 | 148.6364 | GPC [view] | Field Ops | Giant Piston Corer CPH and GPC foul issue - Begin CPH recovery to inspect | ||
2021-12-02 05:09 [view ] | -43.2447 | 148.6378 | GPC [view] | Field Ops | Giant Piston Corer recover cph:trigger arm missing | ||
2021-12-02 05:10 [view ] | -43.2447 | 148.6381 | GPC [view] | Field Ops | Giant Piston Corer re deploy CPH | ||
2021-12-02 05:19 [view ] | -43.2453 | 148.6396 | GPC [view] | Field Ops | Giant Piston Corer trigger secured inboard | ||
2021-12-02 05:22 [view ] | -43.2452 | 148.6401 | GPC [view] | Field Ops | Giant Piston Corer hoisting on 7t w | ||
2021-12-02 05:26 [view ] | -43.2452 | 148.6406 | GPC [view] | Field Ops | Giant Piston Corer GPC secured into CPH | ||
2021-12-02 05:35 [view ] | -43.2445 | 148.6417 | GPC [view] | Field Ops | Giant Piston Corer GPC landed and secured | ||
2021-12-02 07:54 [view ] | -43.2295 | 148.5923 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-02 07:54 [view ] | -43.2295 | 148.5923 | SVP [view] | SVP | Sound velocity probe event Profile also added to Ranger2 USBL system | ||
2021-12-02 07:55 [view ] | -43.2295 | 148.5919 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Start mapping following coring operations | ||
2021-12-02 08:17 [view ] | -43.2337 | 148.5800 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stnadingby for weather awaiting cmaera deployment | ||
2021-12-02 08:17 [view ] | -43.2337 | 148.5800 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Standingby for weather awaiting camera deployment | ||
2021-12-02 08:17 [view ] | -43.2337 | 148.5800 | EM122 [view] | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Standingby for weather awaiting camera deployment | |||
2021-12-02 09:02 [view ] | -43.2583 | 148.5302 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Restart mapping following standyby for camera ops | ||
2021-12-02 09:13 [view ] | -43.2635 | 148.5161 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-02 09:39 [view ] | -43.2725 | 148.4878 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Start following coring operations | ||
2021-12-02 09:40 [view ] | -43.2728 | 148.4868 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Start following coring operations | ||
2021-12-02 09:44 [view ] | -43.2738 | 148.4830 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Adjust window size due to continental slope | ||
2021-12-02 10:03 [view ] | -43.2802 | 148.4646 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-02 11:14 [view ] | -43.2641 | 148.2820 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-02 11:51 [view ] | -43.2528 | 148.2433 | Deep Towed Camera [view] | Deep Towed Camera System event | |||
2021-12-02 15:38 [view ] | -43.2331 | 148.6666 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-02 16:04 [view ] | -43.1709 | 148.7287 | TSG [view] | UWY Seawater | Thermosalinograph events | ||
2021-12-02 16:05 [view ] | -43.1684 | 148.7312 | pCO2 [view] | UWY Seawater | pCO2 event | ||
2021-12-02 16:05 [view ] | -43.1659 | 148.7337 | Fluorometer [view] | UWY Seawater | Underway Fluorometer | ||
2021-12-02 17:45 [view ] | -43.2337 | 148.6425 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop logging stationary on site | ||
2021-12-02 17:51 [view ] | -43.2335 | 148.6417 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging stationary on site | ||
2021-12-02 17:51 [view ] | -43.2334 | 148.6416 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging stationary on site | ||
2021-12-03 02:15 [view ] | -43.2350 | 148.6434 | GPC [view] | Field Ops | Giant Piston Corer Kasten prep complete. deck take 5 for loading into CPH start. | ||
2021-12-03 03:14 [view ] | -43.2363 | 148.6429 | GPC [view] | Field Ops | Giant Piston Corer Kasten toolbox complete. Bosun checking K75 load . preping to deploy. | ||
2021-12-03 03:50 [view ] | -43.2418 | 148.6463 | GPC [view] | Field Ops | Giant Piston Corer stand down - 5 min re hydration break | ||
2021-12-03 04:18 [view ] | -43.2474 | 148.6493 | GPC [view] | Field Ops | Giant Piston Corer chp with kasten deployed | ||
2021-12-03 04:57 [view ] | -43.2571 | 148.6553 | GPC [view] | Field Ops | Giant Piston Corer kasten recovery begins | ||
2021-12-03 06:59 [view ] | -43.2769 | 148.6297 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Commencing transit back to Hobart | ||
2021-12-03 07:00 [view ] | -43.2770 | 148.6275 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Commencing transit back to Hobart | ||
2021-12-03 07:00 [view ] | -43.2770 | 148.6275 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Commencing transit back to Hobart | ||
2021-12-03 08:37 [view ] | -43.2835 | 148.3267 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-03 09:34 [view ] | -43.2874 | 148.1446 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop as vessel transits up shelf | ||
2021-12-03 09:35 [view ] | -43.2874 | 148.1446 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Mapping on shelf | ||
2021-12-03 09:35 [view ] | -43.2875 | 148.1415 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Settings changed for onshelf mapping | ||
2021-12-03 09:37 [view ] | -43.2875 | 148.1385 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Settings changed for onshelf mapping | ||
2021-12-03 12:40 [view ] | -43.2915 | 147.7568 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-03 13:52 [view ] | -43.2491 | 147.7124 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start backscatter line | ||
2021-12-03 15:02 [view ] | -43.1963 | 147.6208 | SVP [view] | SVP | Sound velocity probe event Rapidcast deployment | ||
2021-12-03 15:29 [view ] | -43.1763 | 147.5866 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-03 17:55 [view ] | -43.0860 | 147.4012 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event stop logging stationary waiting for delivery | ||
2021-12-03 17:55 [view ] | -43.0860 | 147.4013 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event stop logging waiting for delivery | ||
2021-12-03 17:56 [view ] | -43.0860 | 147.4013 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event stop logging waiting for delivery | ||
2021-12-03 20:07 [view ] | -43.0875 | 147.4065 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Trigger mechanism on board moving off to CTD maintenance location | ||
2021-12-03 20:08 [view ] | -43.0874 | 147.4089 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Start logging SBP120 | ||
2021-12-03 20:09 [view ] | -43.0873 | 147.4118 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Start logging | ||
2021-12-03 23:22 [view ] | -43.3469 | 148.1989 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-03 23:23 [view ] | -43.3478 | 148.2033 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Start logging | ||
2021-12-03 23:24 [view ] | -43.3478 | 148.2033 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Stop Logging | ||
2021-12-03 23:46 [view ] | -43.3681 | 148.2979 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-04 00:37 [view ] | -43.4255 | 148.5117 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-04 01:33 [view ] | -43.4603 | 148.6364 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop logging on CTD Test Station | ||
2021-12-04 01:34 [view ] | -43.4603 | 148.6364 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging on CTD Test station | ||
2021-12-04 13:55 [view ] | -43.6469 | 148.3207 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Commence seabed mapping for transit to GC Site | ||
2021-12-04 19:22 [view ] | -43.2329 | 148.6428 | GPC [view] | Field Ops | Giant Piston Corer Go/NoGO /toolbox discsussion 0600 -0620. corer assembly begins. | ||
2021-12-04 20:26 [view ] | -43.2321 | 148.6425 | GPC [view] | Field Ops | Giant Piston Corer breakfast complete-Barrels install complete. | ||
2021-12-04 21:23 [view ] | -43.2328 | 148.6426 | GPC [view] | Field Ops | Giant Piston Corer Build complete. Pre-start assembly inspection underway | ||
2021-12-04 22:06 [view ] | -43.2328 | 148.6426 | GPC [view] | Field Ops | Giant Piston Corer Take 5 CPH deployment - begin to maneuver | ||
2021-12-04 22:46 [view ] | -43.2328 | 148.6426 | GPC [view] | Field Ops | Giant Piston Corer Cph deployed | ||
2021-12-04 22:57 [view ] | -43.2328 | 148.6426 | GPC [view] | Field Ops | Giant Piston Corer Clearer being deployed | ||
2021-12-04 23:03 [view ] | -43.2328 | 148.6426 | GPC [view] | Field Ops | Giant Piston Corer Recover cph | ||
2021-12-05 00:00 [view ] | -43.2338 | 148.6430 | GPC [view] | Field Ops | Giant Piston Corer 10 m/m | ||
2021-12-05 00:07 [view ] | -43.2338 | 148.6431 | GPC [view] | Field Ops | Giant Piston Corer Unload | ||
2021-12-05 01:17 [view ] | -43.2344 | 148.6440 | GPC [view] | Field Ops | Giant Piston Corer 100mtr stop. take 5 complete. partial deploy CPH start. | ||
2021-12-05 02:44 [view ] | -43.2386 | 148.6405 | GPC [view] | Field Ops | Giant Piston Corer Barrels dissembled | ||
2021-12-05 05:09 [view ] | -43.2727 | 148.6246 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Mapping on transit to Jutzeler coring site | ||
2021-12-05 05:10 [view ] | -43.2750 | 148.6220 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event | ||
2021-12-05 08:01 [view ] | -43.6217 | 148.1979 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-05 13:51 [view ] | -44.3965 | 147.2087 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-05 14:20 [view ] | -44.4498 | 147.1228 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Restart logging following dropout | ||
2021-12-05 14:34 [view ] | -44.4741 | 147.1022 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Commence Jutzeler coring site SBP survey | ||
2021-12-05 14:55 [view ] | -44.5122 | 147.0736 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Complete SBP corer survey line 1 | ||
2021-12-05 15:15 [view ] | -44.5062 | 147.0510 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Restart logging following loss of bottom track | ||
2021-12-05 15:36 [view ] | -44.4812 | 147.0273 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event New line on turn to SBP Location | ||
2021-12-05 15:38 [view ] | -44.4832 | 147.0270 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Start logging SBP line on turn | ||
2021-12-05 16:20 [view ] | -44.5035 | 147.0629 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event New SBP track line | ||
2021-12-05 16:20 [view ] | -44.5032 | 147.0604 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event New SBP Track line | ||
2021-12-05 17:30 [view ] | -44.4241 | 146.9899 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Turn to cover seamount | ||
2021-12-05 17:30 [view ] | -44.4240 | 146.9942 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event SBP line to cover seamount | ||
2021-12-05 17:55 [view ] | -44.4542 | 147.0632 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event New line for transit to core location | ||
2021-12-05 18:34 [view ] | -44.5078 | 147.0501 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop logging stationary on site | ||
2021-12-05 18:34 [view ] | -44.5078 | 147.0501 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging SBP stationary on site | ||
2021-12-05 20:36 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer Deck tool box complete - begin CPH operation | ||
2021-12-05 20:56 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer Pilot Being deployed | ||
2021-12-05 21:08 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer trigger issue, removing trigger | ||
2021-12-05 21:13 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer trigger re assembled to core head. Better orientation for ropes | ||
2021-12-05 21:32 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer GPC being lefted from CPH | ||
2021-12-05 21:39 [view ] | -44.5071 | 147.0514 | GPC [view] | Field Ops | Giant Piston Corer partial recover of CPH- check for foul. good. full deploy call made to 1500 60mm | ||
2021-12-05 21:46 [view ] | -44.5071 | 147.0513 | GPC [view] | Field Ops | Giant Piston Corer CPH on deck | ||
2021-12-05 22:22 [view ] | -44.5071 | 147.0512 | GPC [view] | Field Ops | Giant Piston Corer stop at 2300 | ||
2021-12-05 22:41 [view ] | -44.5071 | 147.0512 | GPC [view] | Field Ops | Giant Piston Corer Offload | ||
2021-12-05 23:37 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer winch stopped at 100mtrs below | ||
2021-12-05 23:43 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer CPH deploy | ||
2021-12-05 23:58 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer pilot core recovered | ||
2021-12-05 23:59 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer Pilot core recovered | ||
2021-12-06 00:07 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer Trigger mechanism recovered | ||
2021-12-06 00:16 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer GPC recovered into the CPH | ||
2021-12-06 00:24 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer CPH recovered on board | ||
2021-12-06 01:44 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer bottom barrel lift to extruding stillage | ||
2021-12-06 03:45 [view ] | -44.5287 | 146.9854 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Commence mapping following coring | ||
2021-12-06 03:46 [view ] | -44.5287 | 146.9854 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Commence mapping following coring ops | ||
2021-12-06 07:09 [view ] | -44.5818 | 146.8394 | ADCP [view] | Stop | ADCP Event Stopped while drop keels lowered for GSM noise testing | ||
2021-12-06 07:16 [view ] | -44.5820 | 146.8641 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop recording in prep for drop keel noise test | ||
2021-12-06 07:22 [view ] | -44.5820 | 146.8830 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop Keel fully extended. System Active. Speed 10kts. | ||
2021-12-06 07:33 [view ] | -44.5823 | 146.9255 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop active logging. Switch to passive. | ||
2021-12-06 07:34 [view ] | -44.5823 | 146.9332 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop Keel fully extracted. System in passive. Speed 10kts. | ||
2021-12-06 07:40 [view ] | -44.5823 | 146.9524 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging fully extracted in passive. | ||
2021-12-06 08:00 [view ] | -44.5843 | 147.0014 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop keel in intermedaite position. System active. Speed 10kts. | ||
2021-12-06 08:14 [view ] | -44.5863 | 147.0538 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging active. | ||
2021-12-06 08:15 [view ] | -44.5865 | 147.0575 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop Keel at intermediate depth. System passive. Speed 10kts. | ||
2021-12-06 08:38 [view ] | -44.5927 | 147.1116 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop keel flush with gondola. System active. Speed 10kts | ||
2021-12-06 08:49 [view ] | -44.5946 | 147.1481 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-06 08:49 [view ] | -44.5948 | 147.1515 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging active. | ||
2021-12-06 08:51 [view ] | -44.5950 | 147.1549 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop keel flush with gondola. System passive. Speed 10kts | ||
2021-12-06 08:55 [view ] | -44.5958 | 147.1728 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging intermediate in passive. | ||
2021-12-06 09:08 [view ] | -44.5984 | 147.2020 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop keel flush with hull. System active. Speed 10kts | ||
2021-12-06 09:18 [view ] | -44.6004 | 147.2403 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging active. | ||
2021-12-06 09:20 [view ] | -44.6006 | 147.2442 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Drop keel flush with hull. System passive. Speed 10kts | ||
2021-12-06 09:25 [view ] | -44.6016 | 147.2627 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stoip logging in passive. | ||
2021-12-06 09:26 [view ] | -44.6018 | 147.2665 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Logging back to active | ||
2021-12-06 09:41 [view ] | -44.6054 | 147.3026 | ADCP [view] | Start | ADCP Event | ||
2021-12-06 17:35 [view ] | -44.5084 | 147.1061 | SVP [view] | SVP | Sound velocity probe event SVP applied | ||
2021-12-06 18:04 [view ] | -44.5069 | 147.0501 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop logging stationary on site | ||
2021-12-06 18:04 [view ] | -44.5069 | 147.0503 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging stationary on site | ||
2021-12-06 21:42 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer CPH deployed | ||
2021-12-06 21:51 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer pilot deployed | ||
2021-12-06 21:54 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer trigger installed | ||
2021-12-06 22:06 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer GPC remove from CPH | ||
2021-12-06 22:14 [view ] | -44.5069 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer CPH recovered on board | ||
2021-12-06 22:58 [view ] | -44.5069 | 147.0508 | GPC [view] | Field Ops | Giant Piston Corer Corer No 4 paused at 2200m for 3 min | ||
2021-12-07 00:14 [view ] | -44.5071 | 147.0510 | GPC [view] | Field Ops | Giant Piston Corer CPH partially deployed | ||
2021-12-07 00:21 [view ] | -44.5071 | 147.0510 | GPC [view] | Field Ops | Giant Piston Corer CPH fully deployed as trigger arm out of the water | ||
2021-12-07 00:28 [view ] | -44.5071 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer pilot core recovered | ||
2021-12-07 00:34 [view ] | -44.5071 | 147.0510 | GPC [view] | Field Ops | Giant Piston Corer trigger mechanism recovered | ||
2021-12-07 00:40 [view ] | -44.5071 | 147.0509 | GPC [view] | Field Ops | Giant Piston Corer GPC in CPH | ||
2021-12-07 00:46 [view ] | -44.5071 | 147.0510 | GPC [view] | Field Ops | Giant Piston Corer CPH recovered on board | ||
2021-12-07 09:40 [view ] | -44.2144 | 147.2495 | SVP [view] | GSM | Sound velocity probe event RapidCTD cast to 380m depth | ||
2021-12-07 11:17 [view ] | -44.0246 | 147.4196 | EM122 [view] | GSM | Kongsberg/Simrad EM122 12kHz multibeam echo sounder event Stop mapping as ship transits up slope | ||
2021-12-07 11:17 [view ] | -44.0217 | 147.4196 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event Start mapping as vessel transits up slope | ||
2021-12-07 11:18 [view ] | -44.0217 | 147.4196 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Reconfigure for shallow water operations | ||
2021-12-07 11:19 [view ] | -44.0160 | 147.4198 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop system to reconfigure for shallow water operations | ||
2021-12-07 11:21 [view ] | -44.0131 | 147.4199 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Restart logging for shallow water operations | ||
2021-12-07 11:40 [view ] | -43.9557 | 147.4245 | SVP [view] | GSM | Sound velocity probe event | ||
2021-12-07 15:03 [view ] | -43.4071 | 147.4659 | EM710 [view] | GSM | Kongsberg/Simrad EM710 multibeam echo sounder (70kHz - 100kHz) event New line after backscatter line 2 | ||
2021-12-07 15:21 [view ] | -43.3716 | 147.4833 | SVP [view] | SVP | Sound velocity probe event in2021_e03_rctd_005 | ||
2021-12-07 18:55 [view ] | -43.0718 | 147.4113 | ADCP [view] | Stop | ADCP Event stopping adcps for end of voyage | ||
2021-12-07 19:02 [view ] | -43.0675 | 147.4002 | Instrumentation Clean Seawater Pump [view] | SIT | Stop | in2021_e03 | End of voyage - pump off |
2021-12-07 19:11 [view ] | -43.0574 | 147.3904 | UWY Seawater Lab | UWY Seawater | Events for uwy seawater lab End of voyage: Instrument Clean Seawater pump stopped | ||
2021-12-07 19:15 [view ] | -43.0511 | 147.3892 | TSG [view] | UWY Seawater | Thermosalinograph events End of voyage | ||
2021-12-07 19:15 [view ] | -43.0511 | 147.3892 | pCO2 [view] | UWY Seawater | pCO2 event End of voyage | ||
2021-12-07 19:15 [view ] | -43.0496 | 147.3889 | Fluorometer [view] | UWY Seawater | Underway Fluorometer End of voyage | ||
2021-12-07 19:45 [view ] | -43.0062 | 147.3806 | EK80 [view] | GSM | Simrad EK80 multi-frequency split-beam echosounder (EK80) event Stop logging keels coming home and pilot boarding | ||
2021-12-07 19:45 [view ] | -43.0050 | 147.3804 | SBP120 [view] | GSM | Kongsberg SBP120 Sub-Bottom Profiler event Stop logging finished with SBP | ||
2021-12-07 20:11 [view ] | -42.9727 | 147.3756 | Drop Keel [view] | Drop Keels event End of voyage: Raise both to flush with hull | |||
2021-12-07 22:14 [view ] | Techsas 1 [view] | Stop | Techsas 1 event | ||||
2021-12-07 22:15 [view ] | Techsas 2 [view] | Stop | Techsas 2 event |
Deployments by start time:- Click on column header to sort. Use link on 'Deployment' to see full details. Use the CSV button at the bottom to export data (tab delimited).
Search for deployments from this voyage and others
Deployment | Operation | Station | Cast | Gear | Project | Start and end times | Start Location | End Location | Depth | Description | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Underway System [details] | Air Sampling Inlet Mode,Air Temperature Sensor - ROTRONIC T&RH HC2A-S3,Air Temperature Sensor - ROTRONIC T&RH HC2A-S3,Air Temperature Sensor - ROTRONIC T&RH HC2A-S3,Air Temperature Sensor - ROTRONIC T&RH HC2A-S3,Burket Flow meter,Burket Flow meter,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO Hobart pCO2,CSIRO air sampling inlet,CSIRO air sampling inlet,Depth: TECHSAS-DERIVED. For more information contact the Data Acquisition and Processing group.,Fluorometer Concentration,Fluorometer WSCHL-1441,Gyrocompass,IMOS Port Pyranometer-SN 35122F3,IMOS Port Radiometer-SN 35093F3,IMOS Stbd Pyranometer-SN 35123F3,IMOS Stbd Radiometer-SN 35111F3,IMOS wind monitor,IMOS wind monitor,IMOS wind monitor,IMOS wind monitor,ISAR SST,Kobold MIK-C Flow meter,Kobold MIK-C Fluorometer Flow Meter,Kongsberg Maritime Skipper DL850 doppler log,Kongsberg Maritime Skipper DL850 doppler log,Kongsberg Maritime Skipper DL850 doppler log,Kongsberg Maritime Skipper DL850 doppler log,Kongsberg Maritime Skipper DL850 doppler log,Kongsberg Maritime Skipper DL850 doppler log,LI-COR LI-190 Quantum Sensor,LI-COR LI-190 Quantum Sensor,MAAP Status,Multiangle Absorption Photometer (MAAP),Multiangle Absorption Photometer (MAAP),Optode Dissolved Oxygen Concentration,Optode Dissolved Oxygen Saturation,Optode Water Temperature,Ozone Monitor RVT1,Ozone Monitor RVT1,Ozone Monitor RVT2,Ozone Monitor RVT2,Picarro Greenhouse Gas Spectrometer CO2,CH4,H2o,Picarro Greenhouse Gas Spectrometer CO2,CH4,H2o,Picarro Greenhouse Gas Spectrometer CO2,CH4,H2o,Port Rain Gauge,Port drop keel sensor,RM Young 05106 wind monitor,RM Young 05106 wind monitor,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,RM Young Wind Sensor Type 05106,Remote Temperature (T) - SN 1061,Seapath 330+,Seapath 330+,Seapath 330+,Seapath 330+,Starboard Rain Gauge,Starboard drop keel sensor,ThermoSalinoGraph (TSG)-SN 3439,ThermoSalinoGraph (TSG)-SN 3439,Vaisala Ship's Barometer PTB330 | 2021-11-30 23:00 | 2021-12-07 22:00 | -42.8864 | 147.3388 | ||||||||
ADCP Data [details] | Teledyne RDI ADCP 75 kHz | 2549 | 2021-12-01 09:08 | 2021-12-07 18:16 | -43.1609 | 147.5603 | -43.1092 | 147.4764 | 734 |